working on a bridge job at the moment, pretty big job 1st section starts off as a bird cage is linked with beams over a public walkway/cycleway, we have a minimum height to underside of haki beams 2.750m, but the path is on a slope, why dont the designers have a visit to site 1st before drawing up a job in their ideal environment, where everything is flat, level & perfectly plumb.
i wonder if doctor doom, the man called hayes will actually use his keyboard & type a reply to this. . . .