Ive got a job on top of a 12 story office block,
its an 8m guardrail with netting,
everythings got to go up in a lift so nothing longer than an 8ft can go up,
its on a parapit wall so the workmen can work on top of an air conditioning unit safely,
i cant drill in anywhere but can get a short butt under the air conditioning unit,i also thought about using 56lb weights as kentiledge,
the only thing im worried about is the wind resistance/force against the netting,
need i bother?
dont laugh at my picture:embarrest: