1969scaff
Well-known member
Right here's a good one,putting box ties in around steel total of eight doubles,voice from above"you have to put checks on"What? Yes we had to put them on,so on one elevation with five ties per lift ,six lifts,that's? Correct 480 doubles!!When questioned why they have to be checked got told it's new regs,my reply was of course ********! Any one heard of this before?Same on splice,got to use four swivs per splice or in some cases six,Jesus what are they expecting to happen a nuclear blast?It's scaffolding gone mad.