just started for this company and he keeps banging on about 17 transoms in a loading bay 12 ft long, his reason being the unknown weight of the stone that gets delivered
surely if he was in doubt he would bring the standard spacing in
I asked for the drawing he just replied follow the one that has been erected next to it
is that to the drawing ??
he said that's what the client wants
has the client got a drawing ????
I asked the client he said yeah its somewhere ?????
I cant find it
ask your supervisor to send it across
I was led to believe it was 4 ft centres on bays and 300mm centres on transoms
please could you shed light on this matter
without confirmation from either party I refuse to build this am I right in doing so
surely if he was in doubt he would bring the standard spacing in
I asked for the drawing he just replied follow the one that has been erected next to it
is that to the drawing ??
he said that's what the client wants
has the client got a drawing ????
I asked the client he said yeah its somewhere ?????
I cant find it
ask your supervisor to send it across
I was led to believe it was 4 ft centres on bays and 300mm centres on transoms
please could you shed light on this matter
without confirmation from either party I refuse to build this am I right in doing so