Can you still brace off the hand rail, if you brace every standard. the job is only 17 ft high
foot tie
2m first lift double braced
2m second lift braced off h/rail every standard
1m third lift braced every other as normal
i was told to day that you you carnt brace off the h/rail any more
the job is timber frame . size wise its 40 x 30 x 40 x 30 long and top lift is 5.1 m off slab i know it was allowed a few years ago , have the rules changed
foot tie
2m first lift double braced
2m second lift braced off h/rail every standard
1m third lift braced every other as normal
i was told to day that you you carnt brace off the h/rail any more
the job is timber frame . size wise its 40 x 30 x 40 x 30 long and top lift is 5.1 m off slab i know it was allowed a few years ago , have the rules changed